1 | M/s. GETCO - Vadodara | SITC of 400 KV equipments & materials on EPC basis at 400 KV Ukai S/S | Santej Ahmedabad | 952 lacs | 8 Months | |
2 | M/s. GETCO - Vadodara | SITC of 220KV & 66KV equipments & materials on EPC basis at 220kV Santej S/S | Santej Ahmedabad | 1234 lacs | 12 Months | |
3 | M/s. GETCO - Vadodara | Supply, erection, testing and commissioning of 220kV/66kV Equipments, materials on EPC basis at 220kv Gotri S/S. |
Gotri | 1121 lacs | 12 months | |
4 | M/S ABB | Installation of 220kV & 66kV PASS and its civil foundation work at 220kV GETCO Santej SS , GETCO Suva SS & GETCO Gotri SS | Gotri, Santej, Suva | 76 Lacs | 6 months | |
5 |
M/S Inbisco India Pvt Ltd, Sanand
|
Electrification work for M/S Inbisco India Pvt Ltd, Sanand
|
Sanand, Ahmedabad | 67 Lacs | 3 months | |
6 | M/s GETCO - Vadodara | Underground Cable Laying of 66kV and termination work of GETCO at various sites of | Various site | 505 lacs | 2 Years | |
7 | M/s.Arvind Ltd.Santej. | Supply,Erection and testing of Extension of 66KV Switch Yard at Arvind Ltd. Santej. | Santej | 38.66 Lacs | 6 months | |
CONSULATANCY | ||||||
Sr. No. | Name of Client | Job Discription In Brief | Loaction | EXPECTED DURATION | ||
1 | Transworld Terminals Mundra | Electrical system design and project monitoring | Mundra, Kutchh | 3 Months | ||
1 | Paramdham Temple | Electrical Consultancy for Temple Complex | Ahmedabad | 24 months | ||
2 | Jaywin Remedies Pvt Ltd, Chhatral | Design, engg for the Expansion of Plant | Chhatral | 6 months | ||
OPERATION AND MAINTENANCE | ||||||
Sr. No. | Name of Client | Job Discription In Brief | Loaction | EXPECTED DURATION | ||
1 | M/s. GETCO - Vadodara | Operation and maintenance of 66 KV sub stations at 10 locations | Navsari, Vapi, Surat | 360 lacs | 24 Months | |
Energy Audit | ||||||
Sr. No. | Name of Client | Job Discription In Brief | Loaction | EXPECTED DURATION | ||
1 | M/s. New Shorock Mills Ltd - Nadiyad | Energy Audit of Glass Nadiyad Plant | Nadiyad | 1 Month | ||
2 | M/s.IFFCO Kaolol | Energy Audit of Kalol Unit | Kalol | 2 Month | ||
3 | SNL Financial (India) Pvt. Ltd., Ahmedabad. | Electrical Safety Audit of Financial & I.T. Institute. | Ahmedabad | 1 Month |